Sandia’s Z Refurbishment (ZR) Project formally began in February 2002 to increase the Z Accelerator’s utilization by providing the capability to perform more shots, improve precision and pulse shape variability, and increase delivered current. A project update was provided at the 15th International Pulsed Power Conference in 2005 [1]. The Z facility was shut down in July 2006 for structural/infras...Show More
Summary form only given. Sandia's Z Refurbishment (ZR) Project formally began in August 2002 to increase the Z Accelerator's utilization by providing the capability to perform more shots, improve precision and pulse shape variability, and increase delivered current. A project update was provided at the 15th International Pulsed Power Conference in 2005. The Z facility was shut down in July 2006 fo...Show More