1 Background
The SNS line item project start was Oct-98. In the quarter FY99, two workshops were held to explore the option of changing to a Superconducting Linac; this led to a CDR in Nov-99 [1]. The primary requirement for the 1 GeV Linac was a 52-months (later increased to 56- months) schedule including Research & Development, design, fabrication, installation, and checkout. SNS Accelerator Scientific Advisory Committee endorsed the change in Jan-00 and it was then formally reviewed and endorsed by DOE in Mar-00 at the Semi-Annual Review.