Introduction
A. Motivation
The power system is developed in such a way as to ensure its effective and secure operation. However, in some areas large amounts of electric energy are transmitted from power plants over long distances [1] or there are delays in the transmission network development process for reasons over which the investor has no control of [2]. In addition, more electricity generated from renewable energy sources exposes conventional power plants to increased stress during disturbances [3]. In such conditions, a severe disturbance like a fault near the power plant may lead to power system instability.
The loss of transient stability in modern power systems leads to extremely high costs. Since the security of energy supply over time is increasingly important, stability will play a key role in the future. Consequently, utility engineers often introduce various corrective measures, also called emergency controls, to avoid the problem [4].
Dynamic braking using a resistor is considered to be one of the promising solutions and an effective and an economically feasible way to enhance transient stability [5], [6]. An adequate braking resistor application to enhance transient stability of a power system requires selecting: (i) the optimal location, (ii) the parameter of the braking resistor, (iii) the algorithm to control the braking resistor. The location of the (series or shunt) braking resistor on the generator feeder is considered to be the most effective measure to improve transient stability [7]. Regarding the selection of braking resistance, power system operators must take into consideration multiple objectives due to various security limits (i.e. angle and voltage stability limits) and mechanical limits (i.e. turbine-generator shaft fatigue). The selection of braking resistance is followed by the control algorithm determination of the braking resistor.
This paper aims at the comprehensive sizing of the shunt braking resistor (ShBR) for transient state improvement. The problem of shunt braking resistor selection is formulated as a multi-objective optimization problem with such objectives as transient stability, transient voltage response, and mechanical stress of the turbine-generator shaft. A two-stage optimization process has been proposed, which includes: (1) finding a set of Pareto front solutions, (2) determining the best acceptable solution using a fuzzy-set approach.
B. Literature Review
Severe disturbances, such as three-phase short-circuits near the power plant pose a high risk, as the loss of stability can lead to generators tripping and loss of power balance in the electric power system [7]. To reduce the risk of power system instability, various corrective measures are used, including dynamic braking [8], [9]. This paper focuses on using dynamic braking to improve transient stability taking also into account the effect of braking on various aspects of power system operation.
In general, series or shunt elements can be used for dynamic braking [10]. Due to the cost and technical advantages, resistive braking has found a variety of applications [6]. Recently, the application of series fault current limiters has been proposed for power system stability improvement. However, at the current stage of technology development, series elements are mostly used for transient stability enhancement of generators with low and medium power ratings or they need complex connection circuit [6], [11].
As an alternative to series elements, shunt resistors may be used to provide the braking effect. The effect of connecting an ShBR on the power system transient stability is described in [7]. To switch on an ShBR, a mechanical circuit-breaker or power electronics devices can be used. A survey of early application of a mechanically switched ShBR is reported in [12]. It is proposed to apply shunt resistors for braking hydro [13] or thermal [14] units. Current studies on ShBRs mostly focus on brake controller design [15], [16], and coordinated braking with fast valving [9].
Although selecting the parameter of the braking resistor is a very important step when an ShBR is used for transient stability improvement, only a limited research has been conducted on this topic. In [15], a brake controller is designed for one arbitrarily defined value of braking resistor’s resistance. In [9], studies are conducted for a set of the ShBR resistances using an approach similar to the trial and error method. In [16], one objective function, i.e. the maximum power transfer theorem, is used to find the best size of the brake to provide the maximum power transfer which helps to increase the stability margin of the system. If the ShBR is applied to thermal units, the effect on mechanical stress or shaft fatigue must be examined [10]. Therefore, [14] proposes damping of transient torques as a criterion for choosing braking resistor values.
Severe disturbance in a bulk power system simultaneously affects rotor angles, voltage magnitudes, and shaft mechanical stress. Therefore, various security indicators [17], [18] should be considered to assess power system response and to select ShBR resistance. In this case, the selection of the ShBR resistance can be analyzed as a multi-objective task. Out of many multi-objective optimization algorithms [19] available, Non-dominated Sorting Genetic Algorithm-II, a fast and elitist multi-objective genetic algorithm, has been recently applied as an acceptable tool [18], [20].
The authors of this paper note the fact that designing dynamic braking is a multi-objective optimization task that must consider the effect of dynamic braking on various aspects of power system operation, including transient voltage response.
C. Contribution and Organization
The main contributions of this paper are as follows:
This paper proposes a multi-objective heuristics-based optimization method for shunt braking resistor sizing.
A set of objectives and constraints for the comprehensive sizing of shunt braking resistor is proposed.
Single- and multi-objective optimization approaches are compared.
A methodology based on Python programming language is also proposed for solving the multi-objective optimization problem.
This paper is organized in the following way: Section II states the problem, describing selected objectives and constraints which should be considered when selecting the size of an ShBR. Section III provides a brief description of the proposed implementation of the optimization procedure, including multi-objective optimization procedure, NSGA-II algorithm and the best compromise solution method. Section IV describes the results of simulation tests for single-machine and multi-machine test systems. Section V provides conclusions.
Problem Formulation
A. Shunt Braking Resistor
This paper solves the problem of the ShBR sizing for transient state improvement in bulk power systems. The transient state is caused by severe three-phase faults in transmission lines near power plant substation. It is assumed that an ShBR with mechanical circuit breakers for connecting and disconnecting the braking resistor from the circuit is used. The connection of the ShBR to the generator unit’s circuit is shown in Figure 1.
During a system contingency, the ShBR must be connected as fast as possible. In addition, to reduce mechanical stress of the generator shaft, it is assumed that during the transient state the ShBR is connected to the circuit only once to improve first swing stability.
B. Objectives
This paper proposes a multi-objective optimization method for the ShBR resistance sizing. A ShBR connected to the circuit of a generating unit not only affects rotor speed during and after a fault, but also affects nodal voltages and mechanical quantities. On this basis, the proposed approach tries to simultaneously optimize the following three objectives.
1) Transient Angle Stability
Fault clearing time is a major factor in determining the generator stability [7], [17]. The relative difference between the longest clearing time for which the generator will remain in synchronism and the actual clearing time can be provided by a measure of the transient stability margin:\begin{equation*} k_{\textrm {t}} =\frac {t_{\textrm {CCT}} -t_{\textrm {SHC}}}{t_{\textrm {SHC}} }\tag{1}\end{equation*}
In this paper, to assess how the ShBR resistance \begin{equation*} f_{1} \left ({{R_{\textrm {sh}}} }\right)=-k_{\textrm {t}}\tag{2}\end{equation*}
2) Transient Voltage Response
Dynamic braking based on connecting a large artificial load can significantly affect voltage response of a synchronous generator during a fault and after its clearance, which may lead to further instability. Hence, the optimization approach takes into account a quantitative assessment of transient voltage deviation using Voltage Deviation Security Margin Index (VSDMI) introduced in [21]:\begin{equation*} \eta =\frac {s_{\textrm {d}}}{k_{\eta } \left ({{v_{\textrm {n}} -c_{\textrm {cr}}} }\right)t_{\textrm {cr}}}\tag{3}\end{equation*}
Voltage response curve for the definition of the voltage deviation security margin index.
Depending on whether the voltage curve passes the defined voltage security limit \begin{align*}&s_{\textrm {d}} \\&\quad \!\!=\,\,\begin{cases} {k_{\eta } \left \{{{\left ({{v_{\textrm {n}} -v_{\textrm {cr}}} }\right)t_{\textrm {cr}} -\displaystyle \int \limits _{t_{\textrm {s}}}^{t_{\textrm {s}} \!+\!t_{\textrm {cr}}} {\left [{ {v_{\textrm {n}} \!-\!v\left ({t }\right)} }\right]\textrm {d}t}} }\right \}} \\ \qquad \qquad \qquad \qquad \qquad \quad ~\quad \qquad \qquad \;\textrm {if}\;\textrm {t}_{\textrm {b}} \!=\!0 \\ {\displaystyle \sum \nolimits _{\textrm {i=1}}^{\textrm {N}} {\displaystyle \int _{t_{\textrm {si}} }^{t_{\textrm {si}} +t_{\textrm {bi}}} {k_{\eta } \left [{ {v\left ({t }\right)-v_{\textrm {cr}}} }\right]\textrm {d}t,\;\;\textrm {if}\;\;\textrm {t}_{\textrm {b}} \ne 0}}} \end{cases}\tag{4}\end{align*}
The presented Voltage Deviation Security Margin Index allows us to assess transient voltage response regardless of whether security voltage level has been passed or not. Therefore, weighted average of VDSMI indicators is used in this paper to formulate the objective function, which determines the impact of the ShBR resistance on transient voltage response, according to the following equation:\begin{equation*} f_{2} \left ({{R_{\textrm {sh}}} }\right)=-\textrm {max}\left \{{ {\frac {w_{\textrm {h}} \eta _{\textrm {h}g} +w_{1} \eta _{1g}}{w_{\textrm {h}} +w_{1}}} }\right \}_{g=1,2,\ldots,N_{\textrm {G}}}\tag{5}\end{equation*}
3) Mechanical Stress of the Turbine-Generator Shaft
In general, the ShBR can be used for braking hydro or thermal generating units. The application of the ShBR for thermal generating units in particular requires the analysis of the effect it has on the mechanical stress of the turbine-generator shaft. Step changes in power that arise during the ShBR switching can cause extreme mechanical stress in a multi-mass shaft system, with potentially adverse effects on torsional oscillations of the shaft.
As shown in Figure 3, a three-phase short circuit on transmission lines near a power plant substation and the ShBR operation produce transient electrical power in which three step-changes \begin{equation*} f_{3} \left ({{R_{\textrm {sh}}} }\right)=\max \limits _{g=1,2,3,\ldots,N_{\textrm {G}}} \left \{{{\int _{t=0}^{t_{\textrm {k}}} {\left ({{\left |{ {\tau _{g} -\tau _{0}} }\right |} }\right)\textrm {d}t}} }\right \}\tag{6}\end{equation*}
Step changes of generator’s active power output during a fault event with dynamic braking.
C. Constraints
1) Transient Angle Stability Constraints
Transient stability constraints are implemented by using generator rotor angles with respect to the centre of inertia of all the generators. In general, angle transient stability constraints can be expressed as follows:\begin{equation*} \delta ^{\min }\le \delta _{g} \left ({t }\right)-\delta _{\textrm {COI}} \left ({t }\right)\le \delta ^{\max }\tag{7}\end{equation*}
\begin{equation*} \delta _{\textrm {COI}} \left ({t }\right)=\frac {1}{M_{\textrm {T}} }\sum \limits _{g=\textrm {1}}^{N_{\textrm {G}}} {\left [{ {M_{g} \Delta \delta _{g} \left ({t }\right)} }\right]},\quad M_{\textrm {T}} =\sum \limits _{g=\textrm {1}}^{N_{\textrm {G}}} {M_{g}}\tag{8}\end{equation*}
2) Transient Voltage Response Constraints
Transient voltage response of the generating unit terminals, during the fault and after its clearance, is important for maintaining a secure operation of the generating unit auxiliary service. Continuous voltage deviation for a short period may cause serious damage to the auxiliary services motor drives of power units, therefore voltage fault ride-through (FRT) requirements specified in grid codes need to be met [23].
During the fault and after it its clearance, the voltage curve must remain between two limitation curves: the upper one, HVRT (high voltage ride through), and the lower one, LVRT (low voltage ride through). To solve the optimization problem, voltage limitation curves for LVRT and HVRT are established according to documents [23], [24]. Figure 4 shows example limitations of voltage determined by two broken lines: the upper HVRT and the lower LVRT, and also shows an example of dynamic voltage response during a fault in the transmission line and after its clearance (bold line).
The FRT transient voltage response constraints can be expressed by the following integral indicators:\begin{align*} h_{1} \left ({{R_{\textrm {sh}}} }\right)=&\int \limits _{0}^{t_{\textrm {k}}} {\left |{ {\varepsilon _{\textrm {HVRT}} \left ({t }\right)} }\right |} \textrm {d}t= \textrm {0} \tag{9}\\ h_{2} \left ({{R_{\textrm {sh}}} }\right)=&\int \limits _{0}^{t_{\textrm {k}}} {\left |{ {\varepsilon _{\textrm {LVRT}} \left ({t }\right)} }\right |} \textrm {d}t= \textrm {0}\tag{10}\end{align*}
\begin{align*} \varepsilon _{\textrm {HVRT}} \left ({t }\right)=&V\left ({t }\right)-HVRT\quad \textrm {for}\;V\left ({t }\right) > HVRT \tag{11}\\ \varepsilon _{\textrm {HVRT}} \left ({t }\right)=&0\quad \textrm {for}\;V\left ({t }\right)\le HVRT \tag{12}\\ \varepsilon _{\textrm {LVRT}} \left ({t }\right)=&V\left ({t }\right)-LVRT\;\textrm {for}\;V\left ({t }\right) < LVRT \tag{13}\\ \varepsilon _{\textrm {LVRT}} \left ({t }\right)=&0\quad \textrm {for}\;V\left ({t }\right)\ge LVRT\tag{14}\end{align*}
3) Mechanical Stress of Turbine-Generator Shaft Constraints
For a switching operation in which the ShBR is switched off, the following constraint can be applied, according to guidance in [25]:\begin{equation*} \Delta P_{3} \le 0.5P_{\textrm {n}}\tag{15}\end{equation*}
From (15) it results that ShBR switching off should result in step changes in real power of generating units less than a half of their rated power
D. Optimization Problem
The multi-objective optimization model which minimizes three objectives (2), (5) and (6) for optimal resistance sizing of the ShBR can be expressed as follows:\begin{align*} \min \limits _{R_{\textrm {sh}}} F\!=\!\left [{ {f_{1} \left ({{R_{\textrm {sh}},{\mathbf { x}},{\mathbf { u}},{\mathbf { y}}} }\right),f_{2} \left ({{R_{\textrm {sh}},{\mathbf { x}},{\mathbf { u}},{\mathbf { y}}} }\right),f_{3} \left ({{R_{\textrm {sh}},{\mathbf { x}},{\mathbf { u}},{\mathbf { y}}} }\right)} }\right] \\\tag{16}\end{align*}
\begin{align*} \begin{cases} {{\dot {\mathbf {u}}}={\mathbf { h}}\left ({{{\mathbf { x}},{\mathbf { u}},{\mathbf { y}}} }\right)} \\ {0={\mathbf { g}}\left ({{{\mathbf { x}},{\mathbf { u}},{\mathbf { y}}} }\right)} \end{cases}\tag{17}\end{align*}
Besides, it is assumed that the ShBR rated resistance can be selected from a limited range of possible values specified by the user. Thus, constraints for \begin{equation*} R_{\textrm {sh}\min } \le R_{\textrm {sh}} \le R_{\textrm {sh}\max }\tag{18}\end{equation*}
Implementation of the Optimization Procedure
A. Multi-Objective Optimization Procedure
To obtain multi-objective sizing of the ShBR, the calculation procedure presented in Figure 5 has been formulated. The optimization process is as follows.
The main component of the methodology presented below is a Python-based program which includes modules responsible for conducting the respective steps of the optimization process. Transient state simulations were conducted in DIgSILENT PowerFactory power systems analysis software. One of the user-written modules allows us to run PF software in the calculation engine mode to maintain a fast and reliable data exchange of the results between simulation and optimization packages.
The user-made Python module responsible for the calculation of the objectives then processes the obtained simulation result model and the values of the constraints functions. In the next steps, prepared data sets with the results are used by a Python-based NSGA-II implementation of the optimization algorithm. The presented steps are consecutively repeated to obtain the following populations forming the set, including feasible Pareto optimal solutions. Finally, the NSGA-II algorithm results are processed by a fuzzy logic selection method to find the best compromise solution for the analyzed problem.
B. NSGA-II Algorithm
The considered optimization problem was solved using Python implementation of the multi-objective evolutionary NSGA-II algorithm (Nondominated Sorting Genetic Algorithm), which is presented in detail in [26]. The presented algorithm is a significant expansion of the original NSGA concept due to the following improvements [27]:
reduction of the algorithmic complexity to
, whereO(\kappa ^{2}c) is the size of the population and\kappa is the number of objectives;c replacement of the original sharing method by a niching technique without additional parameters;
implementation of elitism in order to improve the algorithm convergence.
Due to the above features, NSGA-II method is considered to be one the most effective reference methods for multi-objective evolutionary optimization, therefore it was chosen to solve the considered problem. A brief illustration of the algorithm procedure is presented in Figure 6.
In the initial step of the algorithm,
Once initial parent and offspring populations are prepared, consecutive
The next population
C. Best Compromise Solution
Once the Pareto set
Membership functions describe the optimization degree of a result, taking into account each objective function. The fuzzy membership of \begin{align*} \mu _{ij} \left ({{R_{\textrm {sh}}} }\right)=\begin{cases} {1,} & {\textrm {if}} ~{f_{ij} \le f_{i}^{\min }} \\ {\dfrac {f_{j}^{\max } -f_{ij}}{f_{i}^{\max } -f_{i}^{\min }},} & {\textrm {if}} ~{f_{i}^{\min } < f_{ij} < f_{i}^{\max }} \\ {0,} & {\textrm {if}} ~{f_{ij} \ge f_{i}^{\max }} \\ \end{cases}\tag{19}\end{align*}
\begin{equation*} \tilde {\mu }_{j} \left ({{R_{\textrm {sh}}} }\right)=\frac {\sum \limits _{i=\textrm {1}}^{N_{1}} {\mu _{ij}} }{\sum \limits _{j=1}^{N_{2}} \sum \limits _{i=\textrm {1}}^{N_{1}} {\mu _{ij}}}\tag{20}\end{equation*}
Simulation Results and Discussion
A. Multi-Machine System Test Case
The multi-objective ShBR sizing procedure for a multi-machine system was performed on the IEEE 10-Machine 39-Bus Power System presented in [29] and shown in Figure 7. Preliminary critical clearing times for various three-phase fault locations were determined. The results show that the shortest critical clearing time is when a fault occurs at busbar B29 (near generator G9). In such a case, generator G9 is the first to lose synchronism and due to that, the ShBR location in the generator G9 feeder and the fault near G9 are selected for the analysis. The ShBR cannot replace fundamental remedial measures to be implemented in the transmission network.
Therefore, only a single ShBR installation to enhance stability is analyzed in the test system considered here.
To illustrate the operation of the ShBR, the operating state of the test system [29] was slightly modified. For the test system under consideration with inactive ShBR, the critical clearing time of generator G9 is 64 ms, which is less than the actual clearing time
B. SHBR Optimization Results
Simulation tests have been performed taking into account single-and multi-objective (two- and three) optimizations. To assess the optimal resistance for the ShBR, a three-phase fault is considered, since such an event has the strongest effect on transient stability. The following fault case is considered: a three-phase fault occurs in line L34 (Figure 7) near substation busbars B29 and that fault is cleared by the line L33 being switched off permanently. If the line L34 is switched off permanently, generator G9 can operate through the line L33, if it manages to remain in synchronism. To calculate objectives
In the case where the three-objective optimization was performed also additional following types of fault events have been taken into account:
two-phase to the ground fault (L-L-G),
two-phase fault (L-L).
Presented fault events (L-L-L, L-L-G, L-L) for the three objective optimization have been analyzed using two different approaches. The first approach includes an individual optimization procedure for each of the particular disturbances. The second approach is based on the analysis of the power system under each of the fault events in the common optimization procedure. The optimized value for each of the three considered objectives have been calculated using a weighted average of the objectives obtained for each disturbance, according to the following formula:\begin{equation*} f_{i}=0.7\cdot f_{i_{L-L-L}}+0.15\cdot f_{i_{L-L-G}}+0.15\cdot f_{i_{L-L}}\tag{21}\end{equation*}
Figure 8 and Figure 9 show the Pareto set
Multi-objective optimization results—obtained Pareto set Gopt as a function of complete set of objectives.
Multi-objective optimization results – obtained Pareto set Gopt three-dimensional plot.
Under the single-objective approach (the results of which are presented in Figure 8.a-c, Pareto sets
Under the single-objective approach, optimum values
Under the two-objective approach (Table 1), the optimum value
However, for the pairs of objectives
Under the three-objective approach considering three-phase disturbance (Table 1),
Under the three-objective optimization approach considering two-phase and two-phase to the ground fault events (Table 1), optimal resistance values
C. Impact of the Optimal SHBR on Power System Dynamic Response
The impact of the ShBR on power system dynamic response was assessed by calculating the integral squared error of the performance index given by the following formula:\begin{equation*} ISE_{\textrm {y}} =\int \limits _{t=0}^{t_{\textrm {k}}} {\left [{ {e_{y} \left ({t }\right)} }\right]^{2}} \textrm {d}t\tag{22}\end{equation*}
In Table 2, bold numbers denote the results which correspond to minimum values of
The comparison of the dynamic performance of generator G9, in the case of tSHC = 100 ms and different Rsh values considered.
Conclusion
This paper proposes and analyses a multi-objective optimization approach for ShBR sizing. The ShBR sizing problem incorporates three objectives, including transient angle stability, transient voltage response, and mechanical stress of the turbine-generator shaft. To present the complexity of the ShBR optimization process more clearly, studies were conducted for the one-, two- and three-objective approaches. The multivariate optimization analysis shows that the optimal ShBR value is mainly influenced by objectives related to transient stability and voltage dynamic response of the power system. With the above-mentioned criteria taken into account simultaneously, the criterion related to mechanical stress of the turbine-generator shaft affects the selection of the ShBR values only to a slight extent.
The presented multi-objective optimization process confirmed the high efficiency of the electric braking of the rotor of a synchronous generator which contributes to the improvement of the transient stability of the considered power systems. The NSGA-II optimization algorithm provided reliable results in the form of Pareto sets of acceptable solutions from which the final solution has been selected using the fuzzy logic-based method.
Presented research studies can be further developed, focusing on the following aspects:
comparative analysis for different types of braking resistors, especially considering different shunt and series structures,
comprehensive study on the impact of coordinated activation of the electric braking and other supplementary control solutions,
comparative analysis of different multi-criteria optimization methods available for the considered shunt braking resistor dimensioning problem.